SHP-2601-017
DeliveredOrigin
Inuyama Works, Japan
Vessel
MV Kestrel Arrow
Port
Tacoma, WA
Project
P-2601
ETD
Jul 6, 2026
ETA
Aug 5, 2026
Cases
14
Total weight
21,400 kg
Milestone timeline
Factory out
Planned Jul 1, 2026 · Actual Jul 1, 2026
Port ETD
Planned Jul 6, 2026 · Actual Jul 7, 2026
1 day late
Port ETA
Planned Aug 5, 2026 · Actual Aug 4, 2026
1 day early
Customs clear
Planned Aug 8, 2026 · Actual Aug 10, 2026
2 days late
Site delivery
Planned Aug 11, 2026 · Actual Aug 12, 2026
1 day late
Cases
| Case | Work package | Description | Weight | Status | Location |
|---|---|---|---|---|---|
| C-1701 | PL-K02-002 | Vehicle bodies (4) | 1,800 kg | Inventoried | Zone A · Bay 03 |
| C-1702 | PL-K02-002 | Vehicle bodies (4) | 1,800 kg | Inventoried | Zone A · Bay 04 |
| C-1703 | PL-K02-002 | Charging contacts | 950 kg | Arrived | Zone A · Bay 07 |
| C-1704 | PL-K02-002 | Vehicle spares kit | 700 kg | Arrived | Zone C · Bay 01 |
Notes
Bay 2 vehicle bodies and spares. All 14 cases received at site.