Dependencies

Work-package sequencing for P-2601, and the PWBS rules that generate its suggestions.

K01 · OHT rail and supports (3)

PL-K01-001

Bay 1 rail run

Complete

May 11 – Jun 19

PL-K01-002

Bay 2 rail run

Complete

Jun 1 – Jul 10

PL-K01-004

Interbay link rail

In progress

Aug 3 – Sep 11

waits on PL-K01-001waits on PL-K01-002

K02 · OHT vehicles and hoists (2)

PL-K02-001

Bay 1 vehicles

In progress

Aug 10 – Sep 25

Partial

waits on PL-K01-001

PL-K02-002

Bay 2 vehicles

Not started

Sep 7 – Oct 9

waits on PL-K01-002

K03 · OHT power and communication (1)

PL-K03-001

Bay 1–2 power rail

Not started

Sep 14 – Oct 16

waits on PL-K01-004

F01 · Stocker frames and shelving (1)

PL-F01-001

Stocker 1 frame

In progress

Aug 17 – Sep 18

Blocked

F02 · Stocker cranes and controls (1)

PL-F02-001

Stocker 1 crane

Not started

Sep 28 – Oct 30

Blocked

waits on PL-F01-001