Dependencies
Work-package sequencing for P-2601, and the PWBS rules that generate its suggestions.
Suggested rule: K01 → K02
K01 → K02 is a global default, and two K02 packages have no work-package-level dependency recorded yet.
| Upstream | Downstream | |
|---|---|---|
| PL-K01-004 | PL-K02-001 | |
| PL-K01-002 | PL-K02-002 |
K01 · OHT rail and supports (3)
PL-K01-001
Bay 1 rail run
May 11 – Jun 19
PL-K01-002
Bay 2 rail run
Jun 1 – Jul 10
PL-K01-004
Interbay link rail
Aug 3 – Sep 11
waits on PL-K01-001waits on PL-K01-002
K02 · OHT vehicles and hoists (2)
PL-K02-001
Bay 1 vehicles
Aug 10 – Sep 25
Partial
waits on PL-K01-001
PL-K02-002
Bay 2 vehicles
Sep 7 – Oct 9
waits on PL-K01-002
K03 · OHT power and communication (1)
PL-K03-001
Bay 1–2 power rail
Sep 14 – Oct 16
waits on PL-K01-004
F01 · Stocker frames and shelving (1)
PL-F01-001
Stocker 1 frame
Aug 17 – Sep 18
Blocked
F02 · Stocker cranes and controls (1)
PL-F02-001
Stocker 1 crane
Sep 28 – Oct 30
Blocked
waits on PL-F01-001