EVM report
SPI, trend, and PWBS breakdown for a project and date range — printable, and exportable as CSV.
Earned value report
P-2601 — Fab 2 Phase B
As of Aug 21, 2026 · Jul 23 – Aug 21, 2026
SPI
0.91
Behind plan
CPI
0.96
% complete
46%
1,490 of 3,240 items
EAC vs BAC
3,561
+321 items over BAC
Schedule performance trend
PWBS breakdown
| Code | Name | BAC | PV | EV | SPI | Status | Progress |
|---|---|---|---|---|---|---|---|
| K01 | OHT rail and supports | 1,205 | 980 | 1,010 | 1.03 | On plan | |
| K02 | OHT vehicles and hoists | 852 | 410 | 285 | 0.70 | Seriously behind | |
| K03 | OHT power and communication | 640 | 112 | 98 | 0.88 | Behind plan | |
| F01 | Stocker frames and shelving | 397 | 105 | 72 | 0.69 | Seriously behind | |
| F02 | Stocker cranes and controls | 146 | 30 | 25 | 0.83 | Seriously behind |
Bar = earned; tick = planned to date.
Open issues
- BlockingPL-K02-001Aug 15
Hoist mechanisms held in customs — install crew re-tasked to Bay 2 prep.
- MinorPL-K01-004Aug 18
36 hanger bracket sets short in case C-1503; factory air-freighting replacements.
- BlockingPL-F01-001Aug 10
Shelving shipment on the water — frame install cannot start before Sep 4.