SHP-2601-022
At portOrigin
Inuyama Works, Japan
Vessel
MV Harbor Lantern
Port
Tacoma, WA
Project
P-2601
ETD
Jul 20, 2026
ETA
Aug 19, 2026
Cases
9
Total weight
7,300 kg
Milestone timeline
Factory out
Planned Jul 15, 2026 · Actual Jul 15, 2026
Port ETD
Planned Jul 20, 2026 · Actual Jul 21, 2026
1 day late
Port ETA
Planned Aug 19, 2026 · Actual Aug 19, 2026
Customs clear
Planned Aug 24, 2026
Site delivery
Planned Aug 26, 2026
Cases
| Case | Work package | Description | Weight | Status | Location |
|---|---|---|---|---|---|
| C-2201 | PL-K03-001 | Power rail segments | 820 kg | In transit | — |
| C-2202 | PL-K03-001 | Feeder assemblies | 780 kg | In transit | — |
Notes
K03 power-rail segments. Discharged Aug 19, awaiting drayage slot.